Works Package
- Work includes highway & traffic signal junction improvements on A666 Lark Hill & Barbara Castle Way, Blackburn.
- Installation of numerous Traffic & Pedestrian Management set-ups which is in the form of road / footpath closures & diversions
- Take down existing pedestrian guardrail & installation of new guardrail.
- Realign kerblines and improve footways and pedestrian crossing islands.
- Installation of new traffic signal duct & access chambers.
- Proving existing traffic signal ducts.
- Highway drainage adjustments.
- Installation of traffic signs and traffic signal infrastructure.
- Carriageway improvements, planing and resurfacing new carriageway.
- New road markings and road crossing studs

Hazards and Restrictions
- Works are located on the periphery of the busy Town Centre of Blackburn.
- Traffic & pedestrian management set-ups, road / footpath closures and diversions
- Traffic Signal installation, carriageway planing and surfacing work carried out under night time closures.
- The provision of appropriate measures and protection to enable pedestrians and cyclists to safely navigate the works at all times.
- Interface with different contractors using NMS Traffic Management.