Works Package
- Construction of roads & sewers to a new housing development in the village of Chatburn, Clitheroe.
- Topsoil strip and stockpile on site.
- Excavation of deep foul and surface water drainage in hard rock.
- Construction of manhole access chambers with hydrobrake flow control.
- Construction of stormwater attenuation tank 48m x 10m x 1.2m, excavation 3m deep in hard rock

Hazards and Restrictions
- Works on busy construction site in rural village location
- Maintain both safe footpath and vehicular access throughout the works for residents, deliveries, site staff and operatives
- Deep excavations for drainage and stormwater tank. Safety fencing and signing to deep excavations
- Working around various buried services in S278 work areas
- Hard excavation in rock to deep drainage
- Connection onto sewer in existing carriageway under traffic signal control and pedestrian diversion