S278 Work A584 Lytham Road, Warton

Get in touch

Image
June 5, 2025

Works Package

  • The works are the construction of a widened four arm traffic signal controlled junction with ne pedestrian islands & encompass the following:
  • Excavation of existing footpaths to allow new carriageway narrow widening construction
  • CCTV survey of existing drainage & installation of new carriageway drainage and access chambers
  • New kerb alignment and construction of pedestrian crossing islands
  • Supply and installation of footway & carriageway crossing ducting, access chambers, traffic signal pole NAL retention, feeder pillars, electrical connections for the street lighting and traffic signals.
  • Planing out existing carriageway surfacing and laying new binder course and HRA surface course aprox. 4500m2 under temporary closures
  • Plane out existing footway surfacing and laying new binder and surface course
  • Supply and install new street lighting, traffic signs, traffic signals, antiskid surfacing, road markings and cycle markings.
  • Supply and install new extra low voltage traffic signals with crossing facilities including mains supply feeder pillar, controller cabinets, cabling detection, testing and commissioning.
  • Additional works where existing services were encountered within the proposed construction which had not been lowered / diverted by STATS. NMS required to carefully excavate to expose services, lower & protect

Hazards and Restrictions

  • Works completed in the vicinity of 2 schools, village hall, church, residential business properties, BAE Systems Warton Aerodrome requiring access at all times.
  • Maintain both safe footpath and vehicular access through the works for school children and the public. Installation of lane closures with temporary traffic signal control, pedestrian crossing signals and bus stop closures
  • Additional works where existing services were encountered within the proposed construction which had not been lowered / diverted by STATS. NMS required to carefully excavate to expose services, lower & protect

Image
NMS Latest News

fox
Aug 19, 2026
Fox Bacup Quarry – 3,000t of CBGM laid over the weekend

It was a big weekend at the Fox Bacup Quarry. Our teams laid 3,000 tonnes of CBGM to upgrade the site’s main haul route, transforming access and egress for everyone coming through the gate. What makes this one special is that it was delivered entirely in-house by Fox Group companies: J Fishers & Sons supplied CBGM material from the in-house …

Read More

community
Jul 16, 2026
Supporting Hoole St Michael CE Primary School’s Outdoor Redevelopment

At Fox Group, we’re committed to supporting projects that make a real difference in the communities where we live and work. When Hoole St Michael CE Primary School approached us for help with plans to improve several outdoor areas around the school, we were pleased to provide the funding and resources needed to complete the work. Improving Outdoor Spaces for Learning …

Read More

community
Jul 15, 2026
Fox Group Proud to Support Heartbeat with New Arm Bike

Fox Group is proud to have sponsored a new specialist arm bike for Heartbeat, the North West’s leading cardiovascular prevention and rehabilitation charity. The equipment, costing £2,634, will play an important role in supporting both cardiac rehabilitation and stroke rehabilitation classes, helping people regain movement, strength and mobility in their arms as part of their recovery. As a self-funded charity, …

Read More

Image
DISCOVER THE NMS SERVICES
Image
Building and maintaining the North West’s highway network through expertise, collaboration and innovation.
Find Out More